COMPANY OVER TIME

2014 Fault detection on PM
Efficient use of energy
2013 Modernisation of the deinked pulp plant
2012 Noise reduction (Phase 3)
2011 Modernisation of the energy department
2010 Modernisation of the deinked pulp plant
2009 Modernisation of boiler 4 (Phase 2)
2008 Modernisation of paper machine 3
Modernisation of boiler 4 (Phase 1)
2007 Completion of the second phase of the waste water treatment plant
2006 Shutdown of the chemical pulp production plant
2004 Shutdown of paper machine 4
2003 Start-up of co-generation (Phase 1)
Start-up of the deinked pulp plant
Start-up of the waste water treatment plant
Reconstruction ob boiler 5
Reconstruction of the groundwood production plant
Reconstruction of paper machine 2
2001 Modernisation of paper machine 1
2000 The factory is taken over by ČSOB Prague
Modernisation of paper machine 3
Reconstruction of the bleaching plant
1999 Start-up of the sheet cutter 5
1998 The factory is taken over by IPB Prague
1996 The factory is taken over by the ICEC Holding from Ostrava
1990 Reconstruction of paper machine 1
1976 Start-up of the new pulp plant
1975 Start-up of paper machine 3
1972 Start-up of paper machine 4
1963 Start-up of paper machine 2
1955 Start-up of paper machine 1
1946 Restart of the mill
1939 Test pulp production
1938 Selected location in Krško

VIPAP VIDEM KRŠKO d.d.
Tovarniška 18
8270 Krško

Tel: +386 7 481 11 00
Fax: +386 7 492 20 77
e-mail: